Tel: +27 (0) 33 345 3284 E-Mail: pmb@sukuma.co.za

Imbali Water

The first phase of the Imbali Midblock Water and Sewer Eradication program is completed. This phase comprised the following:

  • The disconnection of existing midblock water mains following the installation of approximately 14.5km of watermains within the road reserve and the installation of some 660 metered connections to the priority area within Imbali as a result of the severe supply and pressure restrictions within the area.
  • Pipe bursting of existing sewer mains within the midblock and relaying of a portion of sewer mains where feasible within the road reserve, totaling 2.6km.

 

The total value of the contract amounted to approx. R 8 million